When an AI data center site depends on onsite natural gas generation, ask for the fuel-delivery plan alongside the electrical design. The acquisition team needs to know how much gas the equipment requires, where it will arrive, and what agreements and construction support the proposed service date.
Begin with a written fuel specification from the generation supplier. Give that specification to the gas provider and ask for a serviceability response covering the first phase and any planned expansion.
Calculate the fuel requirement for the proposed output
Ask the generation supplier to provide the heat rate at the intended operating conditions, with the electrical measurement point identified. Match net or gross generation assumptions consistently so auxiliary equipment is accounted for. Request hourly and daily fuel requirements for normal operation, startup and the expected load ramp.
For illustration, assume 10 MW of continuous net generation and a net heat rate of 9 MMBtu per MWh. The assumed requirement is 90 MMBtu per hour, or 2,160 MMBtu over 24 hours. Have the equipment supplier confirm the heat-rate basis and the gas provider confirm the units and heating-value assumptions used in its proposal. These hypothetical figures describe no Ace Miners listing.
Review supply and transportation together
Ask who sells the gas commodity and who transports it to the generator’s delivery point. Request the relevant agreements and identify the capacity, service priority and conditions applying to each part of the arrangement.
EIA explains that power-plant gas transactions generally have supply and delivery components, and either component can be firm or interruptible. Interruptible arrangements can allow service to be curtailed under specified contract conditions. Have your commercial team document how those terms fit the workload’s operating requirements. EIA’s explanation of gas supply and delivery arrangements
Confirm the physical delivery conditions
Send the gas provider the equipment’s required pressure, flow and fuel-quality specifications. Ask for a written response identifying the proposed delivery point and the conditions available there. Have the engineering team identify any regulation, compression, treatment, metering or other equipment assumed between the delivery point and the generators.
Request a drawing showing the proposed connection and the route across the parcel. Ask who designs, owns, operates and maintains each part. Put any required access rights and construction approvals into the project work plan, with the responsible party identified.
Separate existing service from work still to complete
Ask the provider to distinguish infrastructure already operating from proposed additions. For remaining work, request the scope, cost responsibility, equipment milestones and expected commissioning sequence. Track the gas connection separately from generator delivery, electrical acceptance and the permit review.
Consider a hypothetical site with an existing gas connection that serves a smaller industrial load. A proposed generation project needs a larger meter and a new lateral. The buyer should ask for evidence that the provider can deliver the required quantity and pressure after those upgrades, together with the remaining schedule. Record the current service and proposed generation service as separate entries in the diligence file.
Model the delivered cost and interruption scenario
Request a cost breakdown that identifies commodity price, transportation, reservation or minimum commitments, imbalance charges where applicable, and the cost of onsite fuel equipment. Have the finance team show what is included in the delivered electricity estimate and what remains the buyer’s responsibility.
Ask operations how the project responds if gas delivery is reduced or unavailable. Document any alternate electrical supply, workload reduction or recovery plan and have the relevant teams confirm the assumptions. Review those scenarios using our site resilience guide and compare alternatives with the grid-versus-onsite-generation checklist.