An AI data center buyer comparing utility power with onsite natural gas generation needs a common basis for the decision. Start with the facility load you must serve, the date you need it, and the operating conditions your project can accept. Then ask each supplier to price and document that same requirement.
A useful shortlist shows both the cost of delivered electricity and the work still needed to make that electricity available. The lowest quoted energy rate can be less attractive if the delivery date depends on equipment, fuel infrastructure or approvals that remain unresolved.
Compare the same capacity and delivery date
Specify the facility load in megawatts, expected operating hours, and ramp-up by phase. Ask the utility to identify its service commitment, required upgrades and customer obligations. For onsite generation, ask the supplier to show net electrical output under the proposed site conditions, including auxiliary loads, equipment outages and the maintenance plan. Have your electrical engineer reconcile each proposal with the usable IT capacity your design requires.
Put the dates on one schedule. For a utility option, track the service agreement, electrical upgrades, equipment delivery and energization. For gas generation, track the gas delivery arrangement, generation equipment, civil work, applicable approvals and commissioning. Assign an owner and evidence requirement to each milestone.
Build a complete cost comparison
For grid service, request the tariff or supply agreement and an example bill for your expected monthly load profile. Ask how energy charges, demand charges, minimum bills, deposits, standby service and any curtailment arrangements apply to your project.
For gas generation, request the delivered fuel cost and the equipment’s guaranteed heat rate at the intended operating point. A heat rate expresses how much fuel energy is consumed to produce electricity. EIA explains that fuel cost alone leaves out expenses such as operations, maintenance and fixed costs. Include those items when comparing offers. EIA’s explanation of heat rate and generation economics
A worked fuel-cost example
Assume, solely for illustration, delivered gas at $4 per MMBtu and a net heat rate of 9 MMBtu per MWh. Multiplying the two gives $36 per MWh, or 3.6 cents per kWh, for fuel. If gas rises to $6 per MMBtu at the same heat rate, fuel becomes $54 per MWh, or 5.4 cents per kWh.
These are hypothetical inputs. Add equipment ownership or lease payments, maintenance, staffing, insurance and the other costs in the actual proposal. Use a consistent boundary so that charges included in a delivered electricity price are counted once. Ask the supplier to show which costs are fixed, which vary with output and which can change with fuel prices.
Check who will operate and maintain the system
Ask who schedules maintenance, carries replacement-parts inventory, responds to faults and supplies electricity during a planned outage. Where the design includes grid backup or export, request the applicable utility requirements and charges. If combined heat and power is proposed, ask your engineering team to identify a practical use for the recovered heat. EPA’s CHP development framework includes capital cost, operations and maintenance, and utility policies in the feasibility review. EPA’s CHP project development guidance
Shortlist with evidence
For each site, record the initial net MW, expansion MW, delivery milestones, total cost assumptions and unresolved dependencies. Keep the supplier’s written commitments alongside your comparison. Use the Ace Miners power verification guide to organize the utility documentation, then check whether the buildable acreage fits the electrical and generation equipment.