Kentucky · Reference KY-005
Kentucky 5MW Mining Site | 3MW Active & Upgrade Potential
A Kentucky mining-site acquisition opportunity with a reported 3MW active base and a pathway to 5MW total capacity. Existing land and electrical infrastructure provide a starting point for continued mining or an AI/HPC conversion assessment.
3MW active reported · upgrade to 5MWPower, land and infrastructure
- Region
- Kentucky
- Power position
- 3MW currently active reported; another 2MW depends on transformer installation and approvals.
- Land / tenure
- Approximately 3.7 acres; land included
- Infrastructure
- Mining containers, electrical equipment and support facilities described.
- Pricing & terms
- Request current commercial terms from Ace Miners.
Development and deployment
The additional 2MW is linked to a transformer upgrade and utility confirmation. A separate longer-term concept contemplates 20MW through a new substation and transmission work. That larger expansion is not included in the current operating-power figure.
What buyers should verify
Inspect transformers, distribution gear and containers; reconcile equipment ratings with deliverable load. Confirm utility upgrade scope, timing, fiber service, water, permitting and the cooling and reliability requirements of any proposed AI conversion.
Request a confidential site package
Quote reference KY-005 and share your target MW, required delivery date, preferred transaction structure and intended workload. Ace Miners can discuss current availability and the next step for detailed information. Location, identity and project documents are provided through a controlled process where available.
Public overview based on supplied site materials. Current availability, utility rights, delivery dates and asset inclusions require confirmation. Facility MW, generation capacity and usable IT MW are different measures. AI/HPC suitability depends on project-specific engineering.